Bespoke Construction Progress
Watch a home built
Follow each stage of constructing The Falley on Lot 2 (0.90 acres) — from site clearing to foundation pour, timber framing, and final architectural details. Toggle the CAD Blueprint View to cross-fade between active engineering lines and photorealistic renders.
X_DEV: 0 PXY_DEV: 0 PXLAT: 42.0896000°LON: -72.7349000°
Active Phase01 · Site Preparation
Construction Log
Site Preparation & Excavation
Clearing the 0.90-acre wooded parcel on Lot 2Clearing the designated building pocket, establishing access driveways, installing silt fencing for erosion control, and excavating for the foundation footings.
Engineering Log
Silt fence installed per MA Wetlands Protection Act. Soil compaction testing: 98% dry density. Excavation depth: 4'-6" below finish grade.
Plot Location:42° 05' 22.56" N, 72° 44' 05.64" W
Architect Checklist
- ✓Establish Lot 2 property corners & building setbacks
- ✓Clear timber from the active construction envelope
- ✓Grade construction driveway and stone tracking pad
- ✓Excavate basement cellar hole to sub-grade elevations
Construction Specifications & Codes
- · Frost-Depth Foundation:Concrete footings poured 4'-0" deep, fully engineered to withstand harsh New England winter frost cycles.
- · Timber-Framed rafters: High-grade double-member yellow pine trusses hoisted to create the 18-foot vaulted cathedral great room ceiling.
- · Weather-Tight Barrier: Wrapped in high-performance weather protection with taped joints and flashed rough window openings to ensure maximum thermal efficiency.
- · Premium Exterior Finishes: Styled with white vertical board-and-batten siding, black double-hung high-efficiency windows, and double-pitch standing-seam metal roof highlights.